STATE LANDS (WINNEBA—SITES FOR ELECTRICITY SUBSTATIONS) INSTRUMENT, 1998 (EI 10).

 

WHEREAS it appears to the President that the land described in the Schedules to this Instrument is the land required in the public interest.

NOW THEREFORE, in exercise of the powers conferred on the President by subsection 1 of section 1 of the State Lands Act, 1962 (Act 125) this Instrument is made this 21st day of April, 1998.

The land specified in the Schedules hereto is hereby declared to be land required in the public interest.

SCHEDULE “A”

ALL THAT PIECE OF LAND known as Site for Electricity Substation containing an approximate area of 0.05 acre situate at Winneba in the Awutu-Effutu-Senya District in the Central Region of the Republic of Ghana adjoining and lying to the South-east of unnamed road and bounded on the North-east by an existing building measuring 40 feet more or less on the South-east by open space measuring 52 feet more or less on the South-west by open space measuring 40 feet more or less on the North-west by the said unnamed road measuring 52 feet more or less which piece of land is more particularly delineated on Plan No. LD.10914/83722 hereto attached and thereon shewn edged pink.

SCHEDULE “B”

ALL THAT PIECE OF LAND known as Site for Electricity Substation containing an approximate area of 0.04 acre situate at Winneba in the Awutu-Effutu-Senya District in the Central Region of the Republic of Ghana lying on the South-east of a proposed road and bounded on the North-east by open space measuring 50 feet more or less on the South-east by open space measuring 33 feet more or less on the South-west by open space measuring 50 feet more or less on the North-west by open space measuring 32 feet more or less which piece of land is more particularly delineated on Plan No. LD.10913/83701 hereto attached and thereon shewn edged pink.

SCHEDULE "C”

ALL THAT PIECE OF LAND known as Site for Electricity Corporation of Ghana Substation containing an approximate area of 0.0229 acre situate at Winneba in the Effutu-Awutu-Senya District in the Central Region of the Republic of Ghana lying to the West of an existing motor road and bounded on the North-east by open space measuring 28.5 feet more or less on the South-east by open space measuring 37 feet more or less on the South-west by open space measuring 29.4 feet more or less on the North-west by open space measuring 39.8 feet more or less which piece or parcel of land is more particularly delineated on Plan No. LD.10593/83697 hereto attached and thereon shewn edged pink.

By Command of the President.

CLETUS A. AVOKA

Minister for Lands and Forestry

Date of Gazette Notification: 12th June, 1998.

 